at88rf1354 ATMEL Corporation, at88rf1354 Datasheet - Page 43

no-image

at88rf1354

Manufacturer Part Number
at88rf1354
Description
13.56 Mhz Type B Rf Reader Specification
Manufacturer
ATMEL Corporation
Datasheet
D.6.
8547A−RFID−10/08
Figure D-9. Typical PCB mounting process flow.
Rework Guidelines
Since solder joints are not fully exposed in the case of QFNs, any retouch is limited to the side fillet. For defects
underneath the package, the whole package has to be removed. Rework of the QFN packages can be a challenge
due to their small size. In most applications, the QFNs will be mounted on smaller, thinner, and denser PCBs that
introduce further challenges due to the handling and the heating issues. Since reflow of the adjacent parts is not
desirable during rework, the proximity of other components may further complicate this process. Because of the
product dependent complexities, the following only provides a guideline and a starting point for the development of a
successful rework process for these packages.
The rework process involves the following steps:
These steps are discussed in the following in more detail. Prior to any rework, it is strongly recommended that the
PCB assembly be baked for at least 4 hours at 125 °C to remove any residual moisture from the assembly.
D.6.1.
The first step in removal of the component is the reflow of the solder joints attaching the component to the board.
Ideally, the reflow profile for the part removal should be the same as the one used for the part attachment. However,
the time above liquidus can be reduced as long as the reflow is complete.
In the removal process, it is recommended that the board should be heated from the bottom side using convective
heaters and hot gas or air should be used on the top side of the component. Special nozzles should be used to direct
the heating in the component area and the heating of adjacent components should be minimized. Excessive airflow
should also be avoided since this may cause the package to skew. Air velocity of 15-20 liters per minute is a good
starting point.
Once the joints have reflowed, the vacuum lift-off should be automatically engaged during the transition from the
reflow to cool down. Because of their small size the vacuum pressure should be kept below 15 inches of Hg. This will
allow the component not to be lifted off if all joints have not been reflowed and avoid pad damage.
1.
2.
3.
4.
5.
Component Removal
Site Redress
Solder Paste Application,
Component Placement, and
Component Attachment.
Component Removal
Component Placement
Pre Reflow Inspection
Solder Paste Printing
Post Print Inspection
13.56 MHz Type B RF Reader
Post Reflow Inspection
Rework & Touch Up
(Visual/X-ray)
REFLOW
43

Related parts for at88rf1354